- March 1, 2021 – Move Into Field Office
- March 4-6, 2021 – Engineering/Layout
- March 8, 2021 – Signs and Maintenance of Traffic
- March 9 & 10, 2021 – Removal of Trees and Clearing
- May 28 – Phase 3 begins
- June 15, 2021 – Curbing and bumpouts formed
- August 20, 2021 – Street was milled and paved, sidewalk benches, trash cans, and bike racks set
- August 20, 2021 – Railroad crossing reconstructed
- November 1, 2021 – Bumpouts landscaped
- November 2021 – Trees planted
- February 2022 – Street lamp posts erected